CONSTRUCTIONAMENDED

Restroom park construction contract finalized with Benchmark

The City of American Canyon previously awarded a construction contract to Benchmark Civil Construction, Inc. for the Northampton and Silver Oak Park Restroom Projects for an original amount of $257,032.00. After three change orders for additional site and utility work, the final contract amount totals $279,305.50, and staff now recommends acceptance of the work as complete and release of retention.

Status
AMENDED
Document date
August 3, 2026
Contract type
CONSTRUCTION
Vendor
Benchmark Civil Construction Inc
Agency
City of American Canyon · CA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$257,032.00 (original); Change Order No. 1: $13,537.50; Change Order No. 2: $1,010.00; Change Order No. 3: $7,726.00; Total: $279,305.50
Contract type
CONSTRUCTION
Renewal
Construction contract awarded December 2, 2025, for $257,032.00 and amended via three change orders to a final total of $279,305.50; current action is acceptance of completion and initiation of statutory retention release period.
Document type
StaffReport
Source document
City of American Canyon Staff Report Notice of Completion for the Northampton and Silver Oak Park Restroom Projects 2026-08-04

Related contracts

Other contracts from Benchmark Civil Construction Inc.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of American Canyon?

Benchmark Civil Construction Inc was awarded this construction contract by City of American Canyon, as recorded on August 3, 2026. The contract value is $257,032.00 (original); Change Order No. 1: $13,537.50; Change Order No. 2: $1,010.00; Change Order No. 3: $7,726.00; Total: $279,305.50.

How much is the Benchmark Civil Construction Inc contract with City of American Canyon worth?

The Benchmark Civil Construction Inc contract with City of American Canyon is valued at $257,032.00 (original); Change Order No. 1: $13,537.50; Change Order No. 2: $1,010.00; Change Order No. 3: $7,726.00; Total: $279,305.50, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a staffreport record.

Where was this contract approved?

This contract appears in City of American Canyon Staff Report Notice of Completion for the Northampton and Silver Oak Park Restroom Projects 2026-08-04 (StaffReport), dated August 3, 2026 from City of American Canyon. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Benchmark Civil Construction Inc hold?

Benchmark Civil Construction Inc may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Benchmark Civil Construction Inc's profile

What is City of American Canyon currently buying?

Explore City of American Canyon's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of American Canyon's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free