Thermalito Water and Sewer District Meeting Minutes February 2026

Change orders approved for Table Mountain pipeline project

Change orders totaling $77,722.70; not to exceed $78,000.00 (total project cost about $373,000)Thermalito Irrigation DistrictSHERWOOD CONTRACTINGFebruary 17, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Board approved two change orders with Sherwood Contracting for additional placement work on the Table Mountain Pipeline Replacement Project in an amount not to exceed $78,000, bringing the project total to about $373,000. The action formally amends the existing construction contract to cover the added work.

Contract Details

Contract Amount

Change orders totaling $77,722.70; not to exceed $78,000.00 (total project cost about $373,000)

Vendor

SHERWOOD CONTRACTING

Agency

Thermalito Irrigation District, CA

Contract Type

CONSTRUCTION

Document Date

February 17, 2026

Renewal Info

Existing construction contract amended via two change orders totaling $77,722.70, with a Board-approved not-to-exceed amount of $78,000 for the additional work.