Banks School District Contract Amendment No. 4 2026-05-06

Banks High School CM/GC GMP Set at $38.2 Million

$38,214,987Banks School District 13P&C CONSTRUCTIONMay 6, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Banks School District executed Contract Amendment No. 4 with P&C Construction, setting a Guaranteed Maximum Price of $38,214,987 for the Banks High School Addition and Remodel CM/GC project. The amendment defines substantial completion by September 13, 2027 and beneficial occupancy by August 12, 2027, and incorporates the latest plans, specifications, and GMP estimate documents.

Contract Details

Contract Amount

$38,214,987

Vendor

P&C CONSTRUCTION

Agency

Banks School District 13, OR

Contract Type

CONSTRUCTION

Document Date

May 6, 2026

Contract Term

Substantial completion no later than September 13, 2027; beneficial occupancy no later than August 12, 2027

Renewal Date

2027-09-13

Renewal Info

This is GMP Amendment No. 4 to the CM/GC Construction Contract dated December 4, 2024, establishing the guaranteed maximum price and contractual completion dates; earlier amendments are not detailed in this document.