Bechtold Paving Advancing Beulah SID 27 Roadwork
Trusted by teams at
Description
The City of Beulah’s SID 27 construction contract with Bechtold Paving, Inc. is underway, with current activities including edge patching along 3rd Ave W and coordination around local fair and parade events. Work will continue into mid-July 2026 within a broader schedule leading to final completion by May 14, 2027.
Contract Details
Vendor
BECHTOLD PAVING INC
Agency
City of Beulah, ND
Contract Type
CONSTRUCTION
Document Date
June 23, 2026
Contract Term
Through approximately mid-July 2026 with overall project completion by May 14, 2027
Renewal Date
2027-05-14
Renewal Info
Project milestones include substantial completion by April 30, 2027 and final completion by May 14, 2027; no explicit renewal terms mentioned.
More from BECHTOLD PAVING INC
More from City of Beulah
City of Beulah Meeting Minutes Beulah SID 27 2026-06-23
City of Beulah Meeting Minutes Beulah SID 27 2026-06-23
City of Beulah Minutes Beulah SID 27 2026-06-16
City of Beulah Minutes Beulah SID 27 2026-06-16
Beulah Pool Board Agenda 2026-06-10
Get alerts on contract renewals, new awards, and vendor activity.
B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.