Civic IQ
CONSTRUCTIONONGOING

City of Beulah Meeting Minutes Beulah SID 27 2026-06-23

Bechtold Paving Advancing Beulah SID 27 Roadwork

City of BeulahBECHTOLD PAVING INCJune 23, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The City of Beulah’s SID 27 construction contract with Bechtold Paving, Inc. is underway, with current activities including edge patching along 3rd Ave W and coordination around local fair and parade events. Work will continue into mid-July 2026 within a broader schedule leading to final completion by May 14, 2027.

Contract Details

Vendor

BECHTOLD PAVING INC

Agency

City of Beulah, ND

Contract Type

CONSTRUCTION

Document Date

June 23, 2026

Contract Term

Through approximately mid-July 2026 with overall project completion by May 14, 2027

Renewal Date

2027-05-14

Renewal Info

Project milestones include substantial completion by April 30, 2027 and final completion by May 14, 2027; no explicit renewal terms mentioned.