SE Diving Contract Amended for Additional Clearwell Work
Trusted by teams at
Description
Spartanburg Water approved a $88,593.07 change order with SE Diving for additional anchor fabrication and installation in Clearwell #3, bringing the revised contract total to $274,128.07 and adding ten project days.
Contract Details
Contract Amount
$88,593.07 (change order); $274,128.07 (revised total)
Vendor
SE DIVING
Agency
Spartanburg Water, SC
Contract Type
CONSTRUCTION
Document Date
October 28, 2025
Contract Term
adds 10 additional days
Renewal Info
Original contract approved May 27, 2025 for $185,535; this is Change Order #1 adding scope, cost, and schedule time.
More from SE DIVING
More from Spartanburg Water
Spartanburg Sanitary Sewer District Commission Agenda 2026-05-26
Spartanburg Sanitary Sewer District Commission Agenda 2026-05-26
The Commissioners of Public Works of the City of Spartanburg Agenda Regular Meeting 2026-05-26
The Commissioners of Public Works of the City of Spartanburg Agenda Regular Meeting 2026-05-26
Spartanburg Sanitary Sewer District Commission Agenda 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.