Mount Pleasant City Council Agenda Packet 2026-04-21

Pay request advanced for Southside WWTP expansion

Original Contract Amount: $40,549,300; Change Orders Total: $815,357.85; New Contract Amount: $41,364,657.85; Current Pay Request #35: $502,131.36; Total payments to date: $36,763,949.27 (before this request $36,261,817.91)City of Mount PleasantDRAKE GENERAL CONTRACTORS LLC (HERITAGE)April 21, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Mount Pleasant City Council will consider approving pay request #35 to Drake General Contractors, LLC (Heritage) for $502,131.36 for expansion work at the Southside Wastewater Treatment Plant. The construction contract, including change orders, totals approximately $41.36 million and has been extended 258 days beyond the original June 3, 2025 substantial completion date.

Contract Details

Contract Amount

Original Contract Amount: $40,549,300; Change Orders Total: $815,357.85; New Contract Amount: $41,364,657.85; Current Pay Request #35: $502,131.36; Total payments to date: $36,763,949.27 (before this request $36,261,817.91)

Vendor

DRAKE GENERAL CONTRACTORS LLC (HERITAGE)

Agency

City of Mount Pleasant, TX

Contract Type

CONSTRUCTION

Document Date

April 21, 2026

Contract Term

Contract Time: 1,008 days; Contract start date: May 15, 2023; Original Substantial Completion: June 3, 2025; Days added to Contract: 258

Renewal Info

Contract has been amended via change orders totaling $815,357.85 and extended by 258 days beyond the original substantial completion date of June 3, 2025. Five percent retainage of $1,934,944.70 is being held pending final completion and acceptance.