Bio‑Nomic Services Nears Completion of Sewer Rehab Phase 1
Trusted by teams at
Description
OJRSA is executing a $3.26 million SCIIP-funded construction contract with Bio‑Nomic Services for Phase 1 of its Consent Order Gravity Sewer Rehabilitation Project, with substantial completion achieved in early April 2026. Recent change orders adjusted material quantities and owner credits, and final punch-list and liquidated damages resolution are in progress.
Contract Details
Contract Amount
$3,262,337
Vendor
BIO-NOMIC SERVICES
Agency
Oconee Joint Regional Sewer Authority, SC
Contract Type
CONSTRUCTION
Document Date
April 28, 2026
Contract Term
January 27, 2025 – April 2, 2026 (substantial completion)
Renewal Date
2026-04-08
Renewal Info
Change Order #8 adjusted contract value; substantial completion letter issued April 8, 2026 and a waiver of liquidated damages is under negotiation.
More from BIO-NOMIC SERVICES
More from Oconee Joint Regional Sewer Authority
Oconee Joint Regional Sewer Authority AgendaPacket Board of Commissioners Meeting 2026-06-01
Oconee Joint Regional Sewer Authority AgendaPacket Board of Commissioners Meeting 2026-06-01
Oconee Joint Regional Sewer Authority Finance & Administration Committee Meeting Agenda Packet 2026-05-26
Oconee Joint Regional Sewer Authority Finance & Administration Committee Meeting Agenda Packet 2026-05-26
Oconee Joint Regional Sewer Authority Finance & Administration Committee Meeting Agenda Packet 2026-05-26
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.