CONSTRUCTIONAMENDED

Lake Arthur Bond Project Amended with $105K Change Order

The Board will consider Change Order No. 3 with Fat Williams Construction on the JDPSB – Lake Arthur Bond project, adding $105,499.00 for additional resurfacing, repairs, and fortification work. The amendment increases the total contract to $4,138,028.00 and extends substantial completion by 27 days to September 21, 2026.

Status
AMENDED
Document date
July 16, 2026
Contract type
CONSTRUCTION
Vendor
Fat Williams Construction
Agency
Jefferson Davis Parish School District · LA

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$105,499.00 (change order); new contract total $4,138,028.00
Contract type
CONSTRUCTION
Contract term
Contract time extended by 27 days to new substantial completion date September 21, 2026
Renewal date
2026-09-21
Renewal
Third change order to the original Lake Arthur Bond project contract, increasing both contract sum and time; new substantial completion date is September 21, 2026.
Document type
Agenda
Source document
Jefferson Davis Parish School Board Agenda 2026-07-16

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by Jefferson Davis Parish School District?

Fat Williams Construction was awarded this construction contract by Jefferson Davis Parish School District, as recorded on July 16, 2026. The contract value is $105,499.00 (change order); new contract total $4,138,028.00.

How much is the Fat Williams Construction contract with Jefferson Davis Parish School District worth?

The Fat Williams Construction contract with Jefferson Davis Parish School District is valued at $105,499.00 (change order); new contract total $4,138,028.00, covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agenda record.

Where was this contract approved?

This contract appears in Jefferson Davis Parish School Board Agenda 2026-07-16 (Agenda), dated July 16, 2026 from Jefferson Davis Parish School District. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Fat Williams Construction hold?

Fat Williams Construction may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Fat Williams Construction's profile

What is Jefferson Davis Parish School District currently buying?

Explore Jefferson Davis Parish School District's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View Jefferson Davis Parish School District's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free