Valve Relocation Construction Contract Awarded to Paulus Engineering

Not to exceed $110,803.87 plus up to $11,080 in change orders (10% contingency)South Coast Water DistrictPAULUS ENGINEERING INCOctober 16, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

South Coast Water District awarded Paulus Engineering, Inc. a construction contract not to exceed $110,803.87, with up to $11,080 in contingency, to relocate air and vacuum valves on the Joint Regional Water Supply System Local Transmission Main. The work commenced January 13, 2025 and was completed March 10, 2025 within the 40 working day contract term.

Contract Details

Contract Amount

Not to exceed $110,803.87 plus up to $11,080 in change orders (10% contingency)

Vendor

PAULUS ENGINEERING INC

Agency

South Coast Water District, CA

Contract Type

CONSTRUCTION

Document Date

October 16, 2025

Contract Term

40 working days (construction began January 13, 2025 and completed March 10, 2025)

Renewal Date

2025-03-10

Renewal Info

One-time construction contract with 10% change order contingency authority; Change Order No. 1 adjusted the contract by -$6,222.00 for additional painting and credits.