CONSTRUCTIONRECOMMENDED

Newkirk Electric Recommended for James Street Breaker Work

Holland Board of Public Works recommended awarding Newkirk Electric a $201,642 construction services contract, including contingency, to replace three 138kV breakers at the James Street Substation. The contract follows a competitive bid process and awaits formal approval as to legal form and budget amendment.

Status
RECOMMENDED
Document date
May 20, 2026
Contract type
CONSTRUCTION
Vendor
Newkirk Electric
Agency
City of Holland city · MI

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Scope & details

The full contract record, as filed.

Contract amount
$183,642 plus 10% contingency of $18,000 (total $201,642)
Contract type
CONSTRUCTION
Contract term
Construction targeted October–November 2026; approximately 4 weeks on-site
Renewal
Single-project construction contract with one-time scope; no renewals indicated.
Document type
AgendaPacket
Source document
City of Holland AgendaPacket Regular Meeting 2026-05-20

Related contracts

Other contracts from Newkirk Electric.

View all →

Frequently asked questions

Common questions about this contract, answered from the record.

Who was awarded the construction contract by City of Holland city?

Newkirk Electric was awarded this construction contract by City of Holland city, as recorded on May 20, 2026. The contract value is $183,642 plus 10% contingency of $18,000 (total $201,642).

How much is the Newkirk Electric contract with City of Holland city worth?

The Newkirk Electric contract with City of Holland city is valued at $183,642 plus 10% contingency of $18,000 (total $201,642), covering construction work.

What type of contract is this?

This is a Construction contract, documented as a agendapacket record.

Where was this contract approved?

This contract appears in City of Holland AgendaPacket Regular Meeting 2026-05-20 (AgendaPacket), dated May 20, 2026 from City of Holland city. Civic IQ extracts contract records directly from agency meeting documents and solicitations.

What other contracts does Newkirk Electric hold?

Newkirk Electric may hold additional government contracts. View their full contract history, the agencies they serve, and total tracked spend on their Civic IQ vendor profile.

View Newkirk Electric's profile

What is City of Holland city currently buying?

Explore City of Holland city's vendors, signed contracts, and active RFPs on their Civic IQ agency profile.

View City of Holland city's profile

Bring us your territory.
We'll show you what is forming.

B2G and SLED sales intelligence. Surface government procurement signals from 80,000+ state, local, and education agencies months before the RFP.

Try Civic IQ for free