City of Boyne City Commission Meeting Agenda Packet 2026-05-12

Hemlock Water Main Material Change Increases Team Elmers Contract

Increase of $22,179.60 (net decrease for Contract 1 becomes $50,976.88)City of BoyneTEAM ELMERSMay 12, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Boyne City staff propose issuing Work Change Directive No. 2 to Team Elmers for the CWSRF Contract 1 Hemlock Street water main project, increasing the contract by $22,179.60. The change replaces planned PVC/HDPE pipe with ductile iron pipe with nitrile joints to meet schedule and regulatory requirements while keeping the overall project under the original budget.

Contract Details

Contract Amount

Increase of $22,179.60 (net decrease for Contract 1 becomes $50,976.88)

Vendor

TEAM ELMERS

Agency

City of Boyne, MI

Contract Type

CONSTRUCTION

Document Date

May 12, 2026

Contract Term

Through June 30, 2026 substantial completion for Hemlock Street work

Renewal Date

2026-06-30

Renewal Info

This is an amendment to the existing CWSRF Contract 1 with Team Elmers, adjusting materials and price; project substantial completion is targeted for June 30, 2026, after which the contract will close out via a balancing change order.

Bring us your territory.
We'll show you what is forming.

See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.

Try Civic IQ for free