Change Order Increases Rocky Hill Road Culvert Contract
Trusted by teams at
Description
The Board approved a change order with Nichols Construction for the Rocky Hill Road culvert replacement project, adding approximately $15,740 in work for tree removal and an upstream culvert. The amendment brings the total project cost to a not-to-exceed $42,220.21.
Contract Details
Contract Amount
Approximately $15,740.00; total project cost not to exceed $42,220.21
Vendor
NICHOLS CONSTRUCTION
Agency
Town of Chadds Ford, PA
Contract Type
CONSTRUCTION
Document Date
April 8, 2026
Renewal Info
Change order adds scope and funding to a 2025-approved culvert replacement contract; no separate renewal terms discussed.
More from NICHOLS CONSTRUCTION
More from Town of Chadds Ford
Chadds Ford Township Board of Supervisors Meeting Agenda May 13 2026
Chadds Ford Township Board of Supervisors Workshop Meeting Minutes 2026-04-22
Chadds Ford Township Board of Supervisors Workshop Meeting Minutes 2026-04-22
Chadds Ford Township Board of Supervisors Workshop Meeting Minutes 2026-04-22
Chadds Ford Township Board of Supervisors Workshop Meeting Minutes 2026-04-22
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.