Shuttle Stop Construction Contract Recommended to Pendleton
Trusted by teams at
Description
Brian Head staff recommend awarding a $722,100 construction contract to Larry A. Pendleton Building, Inc for shuttle stops and crosswalk improvements, following a competitive bid where the firm submitted the lowest responsive bid. The project includes ADA ramp reconstruction and may later be value-engineered through change orders to reduce costs.
Contract Details
Contract Amount
$722,100 (construction of shuttle stops and crosswalks)
Vendor
LARRY A. PENDLETON BUILDING INC
Agency
Town of Brian Head, UT
Contract Type
CONSTRUCTION
Document Date
March 24, 2026
Contract Term
180 days substantial completion / 210 days final completion; liquidated damages $750 per calendar day
Renewal Info
Single-phase construction contract with defined substantial and final completion deadlines; no renewals described. Contract may be amended via change orders to reflect value-engineering changes.
More from LARRY A. PENDLETON BUILDING INC
More from Town of Brian Head
Brian Head Planning Commission Agenda April 21, 2026
Brian Head Town Council Meeting Agenda April 14 2026
Brian Head Town Council Meeting Agenda April 14 2026
Brian Head Town Council Meeting Agenda March 24, 2026
Brian Head Town Council Meeting Agenda March 24, 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.