Bicentennial ballfields shelter foundation change order approved
Trusted by teams at
Description
Campbell County approved Change Order #5 with S&S Builders, LLC, adding $17,990.00 for permitting and pier foundation construction for the new steel shelter at Bicentennial Park softball fields. The shelter-related work is now scheduled for completion by May 15, 2026, increasing the total contract to $1,357,376.84.
Contract Details
Contract Amount
Increase of $17,990.00; new total $1,357,376.84
Vendor
S&S BUILDERS LLC
Agency
Campbell County Public Land Board, WY
Contract Type
CONSTRUCTION
Document Date
May 6, 2026
Contract Term
Shelter component time increased by 28 calendar days; shelter completion May 15, 2026; all other work by April 17, 2026
Renewal Date
2026-05-15
Renewal Info
Change Order #5 increases the contract sum and extends the shelter component schedule by 28 calendar days to May 15, 2026; other work still due April 17, 2026.
More from S&S BUILDERS LLC
More from Campbell County Public Land Board
Campbell County Commissioners Agenda May 2026
Campbell County Commissioners Agenda May 2026
Campbell County Commissioners Agenda May 2026
Campbell County Commissioners Agenda May 2026
Campbell County Commissioners Agenda May 2026
Get alerts on contract renewals, new awards, and vendor activity.
See live SLED buying signals, source docs, decision-makers, contract context, and the next step into your CRM or pipeline.