Malta Town Board Meeting Agenda March 31, 2025

Malta Extends Water District Construction Deadline for Bellamy

Town of MaltaBELLAMY CONSTRUCTION COMPANYMarch 31, 2025

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

The Malta Town Board approved a contract amendment with Bellamy Construction Company for the Maltaville Water District project, extending the contract completion dates due to project delays from equipment manufacturer lead times. The new substantial and final completion dates are September 1 and September 15, 2025, respectively; the contract cost remains unchanged.

Contract Details

Vendor

BELLAMY CONSTRUCTION COMPANY

Agency

Town of Malta, NY

Contract Type

CONSTRUCTION

Document Date

March 31, 2025

Contract Term

Original: substantial completion July 1, 2025 to final completion July 15, 2025; Amended: substantial completion September 1, 2025, final completion September 15, 2025

Renewal Date

2025-09-15

Renewal Info

Amendment extends substantial and final completion dates; no financial amendment reported. Previous contract dates replaced by this change order.