CONSTRUCTIONAMENDED

Town of Johnson Selectboard Meeting Agenda May 4 2026

Library Construction Contract Amended to $1.42 Million

$1,421,750 (revised contract total after Change Order #1)Town of JohnsonBACK 40 BUILDERSMay 4, 2026

Trusted by teams at

Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo
Motive logo
Veritone logo
TerraCycle logo
Cyvl logo
WithersRavenel logo
Derivita logo
Comcate logo
SafeTouch logo
IANS Research logo

Description

Back 40 Builders’ library construction contract has been amended to a revised total of $1,421,750 after Change Order #1, with $872,000 paid and $549,750 remaining. The Selectboard reviewed progress, funding gaps, and risks, and called for a written contingency plan with the contractor and grantor.

Contract Details

Contract Amount

$1,421,750 (revised contract total after Change Order #1)

Vendor

BACK 40 BUILDERS

Agency

Town of Johnson, VT

Contract Type

CONSTRUCTION

Document Date

May 4, 2026

Renewal Info

Contract amount revised via Change Order #1; future amendments or schedule changes are under discussion as the town explores a written Plan B with the contractor and grantor.